Best practice of school renovation #17 Vibeengen Primary School

Best practice of school renovation #17 Vibeengen Primary School

BRIEF INTRODUCTION OF THE PROJECT
The school is a new school completed in 2014 for 500 pupils. The main energy related targets were to achieve the best Danish low-energy class. Partially prefabricated facades are used. The building employs both central and decentral mechanical ventilation in combination with natural ventilation for passive cooling. The energy sources are natural gas and PV’s.

GENERAL INFORMATION
Location: Haslev, Denmark
Project type: New building
Net cost: 21,3 million EURO
Main contractor: BNS
Architect: Arkitema Architects
Building owner: Faxe Municipality
Gross floor area: 6 430 m2
Number of storeys: 2
Construction time: October 2011-april 2014